STATE AID PROJECTS LET BY CONTRACT DURING MARCH, 2005

ALCORN COUNTY- STP-0002(30)BO - 0.236 miles of BRIDGE & APPROACHES on COUNTY ROAD NO. 602. Let to Buddy Ayers Construction, Inc. of Corinth, MS on Friday, March 11, 2005. Contract Amount $399,616.42 ($419,600.00)

BENTON COUNTY- SAP-05(2)M - 1.307 miles of OVERLAY on HICKORY FLAT-CORNERSVILLE ROAD. Let to Rutledge Contractors, Inc. of Tupelo, MS on Wednesday, March 9, 2005. Contract Amount $125,460.35 ($131,700.00)

CALHOUN COUNTY- BR-0007(19)B - 0.509 miles of BRIDGES & APPROACHES on BLUE HOUSE ROAD. Let to Jordan Crane Service, Inc. of Taylorsville, MS on Monday, March 14, 2005. Contract Amount $738,342.46 ($775,300.00)

COVINGTON COUNTY- SAP-16(57) - 0.131 miles of BRIDGE & APPROACHES on WILLIAMSBURG-BASSFIELD ROAD. Let to Jordan Crane Service, Inc. of Taylorsville, MS on Friday, March 11, 2005. Contract Amount $205,000.17 ($215,300.00)

FORREST COUNTY- SAP-18(6)M - 9.745 miles of OVERLAY on ROADS "A" - "D". Let to Warren Paving, Inc. of Hattiesburg, MS on Monday, March 7, 2005. Contract Amount $632,840.62 ($664,500.00)

GRENADA COUNTY- AG-MC-AG23(001) - 5.585 miles of GRADE, DRAIN, BASE & SURFACE on CAMP MCCAIN-HWY 8 ROAD(James H. Biddy Rd.). Let to J. J. Ferguson Sand & Gravel, Inc. of Greenwood, MS on Thursday, March 17, 2005. Contract Amount $1,231,867.94 ($1,385,300.00)

ITAWAMBA COUNTY- SAP-29(5)M - 7.718 miles of OVERLAY on ROADS "A"-"D". Let to APAC-Mississippi, Inc. of Jackson, MS on Friday, March 4, 2005. Contract Amount $520,183.85 ($546,200.00)

LEAKE COUNTY- STP-0521(9)B - 0.056 miles of BOX BRIDGES & APPROACHES on CARTHAGE-THOMASTOWN ROAD. Let to Joe McGee Construction Co., Inc. of Lake, MS on Monday, March 7, 2005. Contract Amount $222,950.92 ($234,100.00)

MARION COUNTY- SAP-46(11)M - 0.073 miles of MAINTENANCE (BRIDGE REPAIR) on BRANDON BAY & MT. SINI ROADS. Let to Fordice Construction Co. of Vicksburg, MS on Tuesday, March 8, 2005. Contract Amount $164,676.25 ($172,900.00)

NEWTON COUNTY- STP-0443(6)B - 2.857 miles of OVERLAY on CHUNKY-DUFFEE ROAD. Let to APAC-Mississippi, Inc. of Jackson, MS on Tuesday, March 22, 2005. Contract Amount $616,891.97 ($647,700.00)

PRENTISS COUNTY- SAP-59(17)S - 12.438 miles of RESEAL on ROADS "A" - "H". Let to Kimes & Stone Construction Co., Inc. of Booneville, MS on Thursday, March 10, 2005. Contract Amount $267,963.53 ($281,400.00)

YALOBUSHA COUNTY- SAP-81(34) - 0.217 miles of BRIDGE & APPROACHES on OLD HIGHWAY NO. 7 ROAD. Let to Prairie Construction, LLC of Tupelo, MS on Monday, March 7, 2005. Contract Amount $567,134.23 ($595,500.00)



LSBP PROJECTS LET BY CONTRACT DURING MARCH, 2005

ATTALA COUNTY- LSBP-04(9) - 0.170 miles of BRIDGE & APPROACHES on ROAD # 3022. Let to Key, LLC of Madison, MS on Monday, March 14, 2005. Contract Amount $523,099.00 ($549,300.00)

CLAY COUNTY- LSBP-13(10) - 0.113 miles of BOX BRIDGE & APPROACHES on JACK FOSTER ROAD. Let to Hall's Construction Co., Inc. of New Albany, MS on Thursday, March 24, 2005. Contract Amount $202,725.88 ($212,900.00)

KEMPER COUNTY- LSBP-35(14) - 0.099 miles of BOX BRIDGES & APPROACHES on FOREMAN-TOLES ROAD. Let to J & M, Inc. of Toomsuba, MS on Monday, March 21, 2005. Contract Amount $87,707.69 ($92,100.00)

NOXUBEE COUNTY- LSBP-52(8) - 0.075 miles of BOX BRIDGE & APPROACHES on LOCKETT ROAD. Let to Ellis Construction Co., Inc. of Columbus, MS on Friday, March 25, 2005. Contract Amount $66,669.45 ($70,000.00)



STATE AID PROJECTS BY FORCE ACCOUNT
AND/OR COUNTY FORCES DURING MARCH, 2005

[ - None - ]