CALHOUN COUNTY PROJECT STATUS
County......: CALHOUN
Project No..: SAP 07 69
Project Type: BASE & DBST
Road Name...:
COLES CREEK ROAD
Termini.....:
BEGIN IN NE 1/4 SEC. 21, T24N,
R8E, THENCE NORTH TO END IN S
E 1/4 SEC. 16, T24N, R8E, OVER
SAP 7(68)
Status......: Complete
Finaled:11/12/2004
Funds.......: $.0
Contractor..: KIMES & STONE CONSTR. CO., INC
|