DESOTO COUNTY PROJECT STATUS
County......: DESOTO
Project No..: SAP 17 7 M
Project Type: OVERLAY, STRIPE & SIGN
Road Name...:
A-CENTER HILL ROAD, B-RED BANKS ROAD
Termini.....:
A-BEGIN IN SEC. 29, T1S, R5W T
HENCE NORTH 2.2 MI. TO END. B
-BEGIN IN SEC. 29, T2S, R5W, T
HENCE NORTH 1.1 MI. TO END
Status......: Complete
Finaled:10/25/2004
Funds.......: $.0
Contractor..: LEHMAN-ROBERTS COMPANY
|