This page created: 04/29/2025 07:23:16 AM
NESHOBA COUNTY PROJECT STATUS
County......: NESHOBA
Project No..: SAP 50 99
Project Type: GRADE, DRAIN, BASE, AND SURFACING
Road Name...:
COUNTY ROADS 262 AND 501
Termini.....:
BEGINNING AT THE MS HWY. 15/ R
OAD 262 INTERSECTION IN SECTIO
N 31, 9, 12, AND RUN EASTERLY
ALONG ROAD 262 FOR 0.52 MILE T
O ROAD 501 INTERSECTION; THENC
E RUN NORTHERLY FOR 0.60 MILES
TO THE BEGINNING OF PREVIOUS
PROJECT NO. SAP 50(76)
Status......: Complete
Finaled:04/22/2011
Funds.......: $.0
Contractor..: King Equipment & Dozer Service
|