This page created: 04/29/2025 07:23:16 AM

                         MADISON COUNTY PROJECT STATUS                         


County......: MADISON
Project No..: SAP 45 4 M
Project Type: REMOVAL OF EXPANSIVE SOILS, ASPHALT LEVELING AND OVERLAY
Road Name...: 
GREEN OAK LANE
Termini.....: 
GREEN OAK LANE FROM U.S. HWY 5
1 TO A POINT 1.5 MILES TO EAST
--PREVIOUS PROJECTS SAP-45(1),
SAP-45(41), SAP-45(46), RS-05
92(3)B
Status......: Complete
              Finaled:09/10/2012
Funds.......: $.0
Contractor..: Hemphill Const.